Beacon Wharf - Notice of Construction - updated May 15, 2012

Commencing the week of June 4, 2012, Ruskin Construction Ltd will be undertaking important structural repairs to the Beacon Wharf.  The construction work is anticipated to take approximately 4 weeks to complete and, for public safety during that time, the wharf will be closed to the public and business activity.  Questions regarding the project may be directed to the Town's Engineering Department at 250-656-4502.

Bowerbank Road Watermain Replacement - updated May 15, 2012

The Town of Sidney will be replacing the existing Water Main on Bowerbank Rd from Amelia Ave to Calvin Ave.

The existing Water main is 200mm (8”) and was installed in 1972.  We will be installing a new 200mm (8”) Plastic Water Main.

The work will commence May 14th, 2012 and will take approximately 4 weeks.

The Town will endeavor to ensure unrestricted pedestrian access to all residences. If you, or any other family members, have any special access requirements, please contact myself in advance so that we can appropriately accommodate your needs.

To assist us in expediting the work, please do not park any vehicles In the construction area during regular working hours. These hours are from 7:00 a.m. to 4:00 p.m., Monday to Friday (except Public Holidays).

Please obey traffic control personnel; they are there for your safety.  The Town will provide additional notices from time to time to keep you informed of the progress of the project.

If you have any questions please call the undersigned at 250-656-1034 or the Engineering Department at 250-656-4502 between 8:30 a.m. and 4:00 p.m., Monday to Friday.

Brad Thomas
Underground Utilities Foreman
or
Mike van der Linden
Manager of Engineering & Environmental Services


Frost Avenue (Lochside Drive to Maryland Drive) - Road, Curb and Sidewalk Work -
updated May 15, 2012

**Note** - upon receiving some opposition to the sidewalk, Council discussed this matter at their regular scheduled Council meeting Monday May 14, 2012 and have directed staff to proceed.

The Town of Sidney will be repairing concrete curbs, installing a new sidewalk (on the south side) and resurfacing Frost Avenue (map of construction area). Construction is anticipated to take six weeks to complete, subject to weather.

To accommodate construction, please do not park any vehicles on Frost Ave between 7:00am and 4:00pm, Monday to Friday. Please make alternate arrangements to park your vehicle outside of the construction area. Vehicle access to your residence will be limited at times. Please obey the traffic control personnel at all times; they are there for your safety.

The construction activities will disturb the boulevard. The Town will endeavor to minimize the impact; however, if you wish to save any existing landscaping features or treasured plantings please remove them. See the map for the extent of construction on your boulevard. You may choose to return the plants to the boulevard after construction is completed. The Town will assist with the removal and replacement of irrigation systems impacted by the Town’s work. Those portions of driveways removed as part of the construction will be reinstated by the Town.

The Town will provide additional notices from time to time to keep you informed on the project’s progress and paving dates.

If you or any other family members have any special access requirements or questions, please contact Adriano Sumberac, Roads Foreman at 250-656-1034 or the Engineering Department at 250-656-4502 between 8:30am and 4:00pm, Monday to Friday.

We apologize in advance for any inconvenience you may experience during this construction, and thank you for your patience and understanding. We hope you enjoy these improvements once they are completed.


 


2012 COMPLETED PROJECTS


Amelia Ave from Bowerbank Rd to Hwy 17 - Storm Drain Replacement - Updated May 2, 2012
The storm drain on Amelia Ave was replaced between Bowerbank Rd and Hwy 17. 

Oakville Ave from Fifth St to Sixth St - Storm Drain Replacement 
The Town of Sidney replaced the Storm Drain on Oakville Ave, between Fifth St and Sixth St in March 2012.

Ocean Ave from Fifth St to Seventh St - Storm Drain Replacement
The Town of Sidney replaced the Storm Drain system on Ocean Ave, from Fifth St to Seventh St in March 2012.  The existing storm drain main was undersized.  Please view the attached map.

Resthaven Dr and Henry Ave - Curbs and Sidewalks
Chew Excavating Ltd did construction activity on Resthaven Dr and Henry Ave January to March 2012.  This work included new curb and gutter and sidewalks. 

Seventh St - Sidewalk
In mid-April 2012, the Town of Sidney Public Works staff and our contractors installed a new interlocking paver sidewalk on the east side of Seventh St from Beacon Ave to James White Blvd.  This work involved replacement of the asphalt driveways with concrete, digging out and prepping the sub base for interlocking pavers, and installation of the pavers along the curb on Seventh St.


Watermain Flushing
The Town of Sidney undertook annual flushing of watermains in February and March 2012.  Flushing began in the southern areas of Sidney and proceeded north.  An Ad appeared in the Peninsula News Review on January 11, 18, 25 and February 1, 2012.

 


 